| Task #: 4037-002 | Responsible: | Est Comp: |
| Increased lift - Gargantuan wants more reserve. | Brabander, Xavier | 05/31/2000 |
| Status: |
| 02/03/1999: Joe says he wants this design "in his back pocket". Today's design is right on the edge and no one is complaining today but he wants to be ready if there is a problem. Philippe has redesigned with lift 1.2 changed to 1.3 but with decreased clamp load. Philippe has also ordered parts for evaluation. |
| Actions Req'd: |
| Order prototype parts. | King, Rick | Complete |
| Task #: 4037-004 | Responsible: | Est Comp: |
| HP 41816 for 4 pcs to evaluate increased lift. Also included 3 add'l parts for reduced fulcrum burst (see task 4037-005). | Ezanno, Phillipe | 12/15/1999 |
| Status: |
|
03/03/1999: Part numbers HM 3228, 3229, 3230, 3231 given to Gargantuan approx. 3/1/99.
05/31/1999: Results?? |
| Task #: 4037-005 | Responsible: | Est Comp: |
| Validation of reduced width of fulcrum in rough casting. HP 41816. | Herican, Ann | 12/01/1999 |
| Status: |
|
03/03/1999: 3 PPCA's from HP 41816 given to M. Pool for burst test. (This HP also had 4 PPCA's for customer eval.) Burst test is complete & results will be faxed on Monday.
05/31/1999: What need's to be done to implement this? |
| Actions Req'd: |
| Mike to determine and list additional tests required to validate this. | Bakers, Mike | 06/10/1999 | |
| Junk to test a report. | Dailey, Fred | Complete |
| Task #: A42-001 | Responsible: | Est Comp: |
| Demonstrate 3 gadget concepts to customer. | Bakers, Mike | 10/30/1999 |
| Status: |
|
09-05-99: 7 proposals were made. Need to decide which 3 to use.
09-15-99: 5 were rejected by mgt. Need to find a 3rd. 09-27-99: 3rd concept was finally approved. Need to get prototypes made quickly. 10-02-99: Customer only liked 1 - 2 more due 11/1. 10-22-99: 2 concepts approved. Need protos but outside machining will be required. |
| Actions Req'd: |
| Find a company to machine the parts in the time req'd. | King, Rick | 10/25/1999 |
| Task #: A42-002 | Responsible: | Est Comp: |
| Build final gadgets to be used. (Mechanicals only) | Brabander, Xavier | 02/01/2000 |
| Status: |
| 10-22-99: Need dwgs finalized before sending to machine shop. May need to source to more than one shop - engrg to evaluate need. |
| Task #: A42-003 | Responsible: | Est Comp: |
| Get sound effect recordings. | Dailey, Fred | 11/15/1999 |
| Status: |
| 10-15-99: Need to review ideas with customer to correlate with movie sound track. |
| Actions Req'd: |
| Set up meeting with customer for review. | Dailey, Fred | 10/18/1999 | |
| Final cost estimate. | Locklin, Cal | 11/30/1999 | |
| Timing schedule ready for distribution. | Bakers, Mike | 11/30/1999 |